         CONTINUITY OF THE MAJOR DEVELOPMENT


         PROJECTS OF THE PORT EQUIPMENT




          Since its establishment, the Agency has undertaken a major investment effort to boost the port offer and enhance the
          infrastructure of Moroccan ports to the ranks of major international ports. The efforts to carry out investment projects
          have been maintained during the period of health crisis, while ensuring compliance with the rules of distancing and
          prevention to contain any risk of spreading the virus in the ANP managed sites.




          The main ongoing projects are related to the mega-program   The adopted Measures in order
          Wessal-Casablanca-Port,  the  construction  of  a  community
          building  and  the  development  of  the  northern  service  at   to contain the risk of Covid-19
          the port of Casablanca, the development of a multipurpose   spread within the worksites
          terminal at the commercial port of Agadir and various projects
          of infrastructure enhancement in the ports managed by the   managed by the Agency
          Agency.
                                                                    In order to prevent any risk of the virus spread among the staff
          Impact of Covid-19                                        involved  in  the  execution  and  management  of  the  various
                                                                    worksites, the Agency has required the hired contractors to take
          on the management of the                                  the necessary measures enabling them guarantee a working

          Agency’s projects                                         environment that complies with health and hygiene standards
                                                                    by strictly observing the health instructions stipulated by the
          The pandemic had affected the achievement pace of some    government and the specialized global institutions.
          infrastructure projects, mainly in terms of:
             •  A decrease and a significant drop in the pace of work.
             •  Great difficulty, or even the impossibility, to support
                the sites with the required resources in order to meet
                the contractual deadlines.
             •  Difficulty  in  supplying  materials,  products  and
                equipment both locally and from overseas.
             •  Movement restrictions on the companies’ staff and
                their effects on the work execution.
          As soon as the containment was lifted, an action plan was
          implemented to make up for the delays while ensuring the
          respect of the prescribed preventive measures.