State of progress of the main projects at the end of December 2020
State of progress New shipyard Improvement of access State of progress
in Casablanca conditions to the port of Assilah
97% 65%
million
2 104 million Dirham tax free 176,4
Dirham tax free
Deepening the maritime
Extension of the Northern terminal docks of the access
service of the port of Casablanca channel and the waterway to the
80% carrier stations in the port of Nador 91%
758,70 million Dirham tax free 132,61
million
Dirham tax free
Construction of liquid
New cruise terminal hydrocarbon pipelines (gasoline,
in the port of Casablanca diesel and kerosene) and their ancillary
93% facilities at the port of Jorf Lasfar 38%
600 million million
Dirham tax free
Dirham tax free 83
Community building Development of the access
of the port of Casablanca road to the new port of Safi
70% 95%
393,87 million Dirham tax free 48,7
million
Dirham tax free
1st phase
Multipurpose terminal in Reinforcement of docks no. 01 75%
the commercial port of Agadir and 02 at the port of Laayoune
90% 2nd phase
306 million Dirham tax free 39,6
million
Dirham tax free
38%
1st phase
Reinforcement of the main Provision and setting up
100% breakwater and mooring of floating wharves,
infrastructures of Marina Smir and rearrangement of the inclined 50%
2nd phase plane in the fishing port of Tan-Tan
97,8 million Dirham tax free 35,6
million
Dirham tax free
52%