PROGRESS OF MAJOR PROJECTS
AS OF DECEMBER 2024
In 2024, several structuring projects were completed, including the new ferry terminal at the Port of Nador and the installation
of photovoltaic panels at Mohammedia and Mehdia. At the same time, new projects were launched, notably at the Port of
Laâyoune, while strategic studies were initiated for the extension of the Port of Tan-Tan and the construction of quays at Safi
Atlantique to support the development of the green hydrogen sector.
66% 74% 67%
Reinforcement Extension
of the port of the main
of Nador’s Jebha port breakwater
main extension at the port of
nd
breakwater 2 phase Casablanca*
*
140 316 1,1
Million Dirham Million Dirham Billion Dirham
* Receiving a financial contribution of * A project of the Ministry
68.4 million dirhams from the ANP. of Equipment and Water, with ANP
as Delegated Project Manager.